Paste Tests/Folders to Target Project Dialog Box

This dialog box enables you to choose how ALM copies a test or test subject across projects.

To access
  1. In the test plan tree or grid, select a test or subject folder.

  2. Right-click and select Copy.

  3. Open another instance of ALM and log in to the project to which you want to paste the tests.

  4. Right-click and select Paste.

Important information

To copy tests across projects, both projects must use the same ALM version and patch level.

User interface elements are described below:

UI Element

Description

Copy tests/test folders and link to existing related entities

ALM copies the tests or subject folders and pastes them into the target project. The copied tests or subject folders are linked to existing test resources and called tests with the same name and path. If a related test resource or a test does not exist in the target project, ALM copies it to the target project.

Copy tests/test folders and related entities

ALM copies the tests or subject folders along with the related test resources and called tests, and pastes them into the target project. If a related test resource or a called test already exists in the target project, the copied related test resource or called test is renamed to resolve the duplicate name.

Copy tests/test folders without copying related entities

ALM copies the tests or subject folders without copying the related test resources or called tests, and pastes them into the target project. The copied items are not linked to any related entities.