Reschedule Release/Cycle/Milestone Dialog Box

This dialog box enables you to reschedule the start and end date of a release, cycle, or milestone.

To access

In the Releases module, right-click a release, cycle, or milestone. Select Reschedule.

Important information
  • When rescheduling a release, the related cycles, milestones, and KPI thresholds are rescheduled accordingly.

  • When rescheduling a milestone, the related KPI thresholds are rescheduled accordingly.

Relevant tasks
See also

User interface elements are described below:

UI Element

Description

Start Date

The date on which the release, cycle, or milestone starts.

End Date

The date on which the release or cycle ends.

Available from: Reschedule Release/Cycle dialog box

Due Date

The date on which the milestone ends.

Available from: Reschedule Milestone dialog box