Paste Test Set Folders To Target Project Dialog Box

This dialog box enables you to select the way in which test sets are copied from one project to another project.

To access
  1. In the source project, right-click a test set or a test set folder and select Copy.

  2. Open the target project in a separate browser window.

  3. In the target project, right-click a test set folder below which you want to insert the copied test set or test set folder, and select Paste.

Important information
  • Test run information is not copied.

  • The source and target projects must use the same ALM version and patch level.

See also

Test Lab Module Window

User interface elements are described below:

UI Element

Description

Copy Test Set Folders and link to existing related entities

ALM copies the test sets or test set folders and pastes them into the target project. The copied test sets or test set folders are linked to existing test resources and called tests with the same name and path. If a related test resource or a test does not exist in the target project, ALM copies it to the target project.

Copy Test Set Folders and related entities

ALM copies the test sets or test set folders along with the related test resources and called tests, and pastes them into the target project. If a related test resource or a called test already exists in the target project, the copied related test resource or called test is renamed to resolve the duplicate name.

Copy Test Set Folders without copying related entities

ALM copies the test sets or test set folders without copying the related test resources or called tests, and pastes them into the target project. The copied items are not linked to any related entities.