Migrate to SaaS
This section provides you with important information on how to migrate from on-premises to SaaS. It's relevant only when you are planning to run the system in a SaaS environment.
In this topic:
Migration plan overview
The following table provides an overview of a SaaS migration plan.
Phase | Customer Action Items | OpenText Action Items |
---|---|---|
Set up new environment (1-2 weeks) |
|
|
Upload data (1-2 weeks) |
|
|
Upgrade sample projects (1-3 weeks) |
|
|
Dry-Run validation (3-8 weeks) |
|
|
Upgrade product (2-4 weeks) |
|
|
Note: This is an overview of a OpenText SaaS migration project plan. Individual tasks specific to the migration will be based on customer readiness. The final project plan will be agreed to between OpenText SaaS and the customer following project kickoff.
Environment diagram
This diagram illustrates the SaaS environment and interaction between OpenText Application Quality Management and customer AUT environments.