Action baseline items

You can action items in a baseline to a new lifecycle state.

PRIVILEGES: Action item to next state to action the items to a valid next state. Action items to any state to action the items to a lifecycle state without a valid transition.

To action baseline items:

  1. In the web client, select a baseline.

  2. Click the Action Baseline Items button.

  3. In the Action Baseline Items dialog box, change the Item Specification Filter, if needed. You can use the following wildcards:

    • Use an underscore (_) to match a single character. For example, d_g matches dog or dig.

    • Use an asterisk (*) or percent sign (%) to match any number of characters. For example, d*g matches dog or drag or dreaming.

  4. From the New Status list, select the next status for the items.

    Note: If you do not have the Action baselines to any state privilege, the new status must be reached from the current status by a single normal lifecycle transition. If you leave the New Status field blank, Dimensions CM automatically selects the next normal lifecycle status.

  5. (Optional) For Action description, enter a comment.

  6. Click OK.

Back to top