PPM Center data transfer during ETL

The following sections describe how PPM data are transferred during the ETL process.

Common dimension data transfer

The COMMON ETL job transfers all PPM data (that fall within the interval defined by the specified start and end dates) and that are shared by Time Management, Resource Management, and Financial Management into the Operational Reporting database schema.

Back to top

Demand Management data transfer

A full ETL for Demand Management(DM) transfers all project data (that fall within the interval defined by the specified start and end dates) from the Demand Management tables into the Operational Reporting database schema. A subsequent incremental DM ETL job loads Demand Management data that have changed since the last DM ETL job run.

Back to top

Portfolio Management data transfer

A full ETL for Portfolio Management (PfM) transfers all project data (that fall within the interval defined by the specified start and end dates) from the Portfolio Management tables into the Operational Reporting database schema. A subsequent incremental PfM ETL job loads Portfolio Management data that have changed since the last PfM ETL job run.

Back to top

Project Management data transfer

A full ETL for Project Management (PM) transfers all project data (that fall within the interval defined by the specified start and end dates) from the Project Management tables into the Operational Reporting database schema. A subsequent incremental PM ETL job loads Project Management data that have changed since the last PM ETL job run.

Back to top

Time Management data transfer

A full ETL for Time Management (TM) transfers all time-sheet data (that fall within the interval defined by the specified start and end dates) from the Time Management tables into the Operational Reporting database schema. A subsequent incremental TM ETL job loads Time Management data that have changed since the last TM ETL job run.

Back to top

Resource Management data transfer

A full ETL for Resource Management (RM) transfers all resource capacity, demand, and actual effort data (that fall within the interval defined by the specified start and end dates) from the Resource Management tables into the Operational Reporting database schema. A subsequent incremental RM ETL job loads Resource Management data that have changed since the last RM ETL job run.

Back to top

Financial Management data transfer

The FM incremental ETL job transfers all Financial Management data (that fall within the interval defined by the specified start and end dates) from the Financial Management tables into the Operational Reporting database schema. A subsequent incremental FM ETL job loads Financial Management data changed since the last FM ETL job run.

Back to top