Analyzing Issue Resolution Time

Program Management provides graphs that let you view how quickly submitted issues (both program issues and project issues escalated to the program level) are getting resolved.

To analyze issue resolution time:

  1. Log on to PPM.

  2. From the menu bar, select Open > Program Management > Issues > Analyze Issue Resolution Time.

    The Issue Resolution: Average Resolution Time page opens.

  3. In the Filter By section, provide the following information:

    Field Name

    Description

    Show

    The type of request to view. Use the default selection (Issues).

    Program Name

    The name of the program for which you want to view issue resolution information.

    Projects

    The names of the projects linked to the selected program for which you want to view issues (escalated) information. If you leave the Projects field empty, Program Management displays issue resolution time information for issues escalated to the program level from all projects linked to the program.

    Resolution Date

    The date range for which you want to view issue resolution information. The time an issue request was submitted is used to calculate issue resolution time.

    Period

    The time increments used to display the issue resolution information. Select either Months (the default selection) or Weeks.

  4. Click Apply.

    Program Managementdisplays a graph that depicts the average (mean) number of days required to resolve the issues that were resolved during the time period you specified. These include program issues and project issues that were escalated to the program level.