Microsoft Project Server Options

Microsoft Project Server options are used to configure the interaction between Microsoft Project Server, Microsoft Project, and the Plug-in for PPM. Use this option to set the project calendar used from the Microsoft Project Server.

Setting the Microsoft Project Server Calendar for the Plug-in for PPM

If a Microsoft Project file is stored on a Microsoft Project Server, the calendar used by the Microsoft Project file is also stored on the Microsoft Project Server. You can configure the Plug-in for PPM to use one of the existing project calendars on the Microsoft Project Server. If you do not configure a calendar (either by not selecting the checkbox or not typing a calendar name), a default calendar, based on the language configured for Microsoft Project, is used.

Set the Microsoft Project Server calendar for the Plug-in for PPM if you are required to use a specific project calendar on the Microsoft Project Server for the Plug-in for PPM. In Project Management-controlled mode, the Plug-in for PPM must be configured to use a calendar on the Microsoft Project Server. The calendar is used by the Plug-in for PPM to synchronize task information during integration.

The following fields are used to configure the Microsoft Project Server calendar used by the Plug-in for PPM.

Table 10-11. Microsoft Project Server Calendar Option

Field

Description

Use custom calendar name for Microsoft Project Server

Select this checkbox to use an existing project calendar from Microsoft Project Server.

calendar name

Type the name of an existing project calendar on the Microsoft Project Server. If a name is not entered, a default calendar, based on the language of Microsoft Project, is used. For example, in English, the default calendar is PPM Calendar. In German, the default calendar is PPM Kalender.

Note: If the calendar name does not exist, the next time you synchronize the project, the synchronization fails.