Scenario 3: Unmet Demand Calculation when Assigned Resources are Partially Allocated
In the following example, Project C requires senior java engineers for four months from October 2011 through January 2012 from US Pool. Staffing requirements are three FTEs for October 2011 through November 2011, tapering off to one FTE for December 2011, and 1/2 FTE for January 2012.
Barbara Getty is a senior java engineer who has 75% of her time allocated from October 2011 through January 2012 to Project C. She is not planning to take any vacation during that time.
Figure B-5. Allocation Detail for Project C in FTEs View shows the allocation detail for Project C in FTEs view.
Figure B-5. Allocation Detail for Project C in FTEs View
Figure B-6. Allocation Detail for Project C in Hours View shows the allocation detail for Project C in hours view.
Figure B-6. Allocation Detail for Project C in Hours View
Table B-5. Example Unmet Demand Calculations for Project C lists the forecasts, assignments, and unmet demand calculations for Project C in FTEs and hours views.
Assignment hours = working hours per day in resource calendar * (working days per month in resource calendar - personal leaving days) * percentage of allocation