Scenario 4: Unmet Demand Calculation when Unmet Demand is Forwarded to Another Pool
In the following example, Project D requires senior java engineers for three months from February through April from US Pool.
Joseph Bank is a senior java engineer who has 50% of his time allocated from February through April to Project D. The rest 50% unmet demand is forwarded to EMEA pool.
Figure B-7. Allocation Detail for Project D in FTEs View shows the allocation detail for Project D in FTEs view.
Figure B-7. Allocation Detail for Project D in FTEs View
Figure B-8. Allocation Detail for Project D in Hours View shows the allocation detail for Project D in hours view.
Figure B-8. Allocation Detail for Project D in Hours View
Table B-6. Example Unmet Demand Calculations for Project D lists the forecasts, assignments, and unmet demand calculations for Project D in FTEs and hours views.
When the position's unmet demand is forwarded to another pool, the position's FTE based forecasted demand is re-calculated using the new pool's calendar, and the unmet demand FTE is re-calculated using the new pool's calendar.