Fields Mapped Between Applications
The following fields are mapped between Project Management and Microsoft Project, grouped by information type (planned and actuals information). All fields are task-level fields unless otherwise noted. See Impact of Microsoft Project Rules on Fields, How Information is Synchronized, and Conditional editing allowed in Project Management for additional considerations about mapping fields.
|
Project Management Field |
Microsoft Project Field |
Additional Information |
|---|---|---|
|
Planned information |
||
|
Milestone |
Milestone |
Milestones retrieved from Microsoft Project must be manually set to 100% complete in Project Management. Milestones retrieved from Project Management do not require updates. See Planned information also . |
|
Predecessor |
Predecessor |
See Planned information, Planned information, Planned information, and Planned information. |
|
Priority |
Priority |
See Planned information. |
|
Resources |
Resources |
See Planned information. |
|
Scheduled Duration |
Duration |
Microsoft Project recalculates duration so that Start, Finish, and Duration are valid. However, if a task is of a fixed duration, only Start and Finish are recalculated. See also Planned information. |
|
Scheduled Effort |
Work |
Scheduled Effort (measured in days) is converted to Work (measured in hours) using the calendar option Hours per day in Microsoft Project. |
|
Scheduled Effort (resource-level) |
Work (resource-level) |
For tasks with more than one assigned resource, the amount of Scheduled Effort/Work assigned to each resource is synchronized. |
|
Scheduled Start Date |
Start |
See Scheduled start and scheduled finish dates, Planned information, Planned information, and Planned information. |
|
Scheduled Finish Date |
Finish |
See Scheduled start and scheduled finish dates, Planned information, Planned information, and Planned information. |
|
Scheduling Constraint/Constraint Date |
Constraint Type/Date |
See Planned information and Planned information. |
|
Task Name |
Task Name |
See Planned information and Planned information. |
|
Actuals information |
||
|
% Complete |
Percent Complete |
See Percent Complete and Percent Work Complete, % Complete When Initializing a Project Management Work Plan from an Existing Microsoft Project Work Plan, and % Complete for Tasks that are Cancelled or On Hold (Bypassed). |
|
Activity |
Custom |
|
|
Actual Duration |
Actual Duration |
See Actual Duration for Tasks and Actual Duration for Summary Tasks/Task Groups. |
|
Actual Effort |
Actual Work |
If any type of effort is tracked in PPM, the link in Microsoft Project between Percent Complete and Percent Work Complete is disabled. See also Actual Effort/Actual Work and Resource Units and Actual Effort and Time Management Integration. |
|
Actual Start |
Actual Start |
When this date exists, Microsoft Project defaults Start to this date. See also Actual Start and Actual Finish and Actual Start of a Task Group. |
|
Actual Finish |
Actual Finish |
When this date exists, Microsoft Project defaults Finish to this date. See also Actual Start and Actual Finish. |
|
Estimated Finish Date |
Finish |
|
|
Estimated Remaining Effort |
Remaining Work |
|
|
Task Description and Notes |
Notes (for tasks) |
|
|
User-defined |
Custom |
|