Resource Utilization Report

This report summarizes the resource utilization information for a specified project. The resources utilization rate is calculated by dividing actual hours by allocated hours.

As a resource manager, you can leverage this report to understand if the resources assigned to the project are well utilized and adjust resources within the project and between projects.

This report contains utilization information during a time period and utilization information for individual resources.

Parameter description
Parameter Description
Begin Period

The first time period for which data is displayed in the report. Select a value from the Available Periods list.

End Period The last time period for which data is displayed in the report. Select a value from the Available Periods list.
Period

The time interval for data displayed in the report. Select one of the following values:

  • Year
  • Half Year
  • Quarter
  • Month
  • Week
Project Name Select the project name from the Project Name list.