Delete a baseline
Delete a baseline when the baseline is no longer required.
PRIVILEGES: Delete Baseline.
You cannot delete a baseline if:
-
It has been used to make a release, unless you delete the release first. For details, see Delete a release.
-
It has been used to create an archive unless you retrieve the archive first. For details, see Administration.
-
It is currently promoted beyond the first stage in the GSL.
Caution: To delete multiple baseline at the same time, use a Dimensions CM command file. This guarantees that each baseline is deleted in turn.
To delete a baseline:
-
Select the baseline.
-
Click Delete.
-
In the Delete dialog box, verify that you have selected the correct baseline, and click OK.
See also: