Migrate ALM to SaaS
This section provides you with important information on how to migrate ALM from on-premises to SaaS. It's relevant only when you are planning to run ALM in a SaaS environment.
Migration plan overview
The following table provides an overview of a OpenText SaaS migration plan.
Phase | Customer Action Items | OpenText Action Items |
---|---|---|
Set up new ALM (1-2 weeks) |
|
|
Upload data (1-2 weeks) |
|
|
Upgrade sample projects (1-3 weeks) |
|
|
Dry-Run validation (3-8 weeks) |
|
|
Upgrade product (2-4 weeks) |
|
|
Note: This is an overview of a OpenText SaaS migration project plan. Individual tasks specific to the migration will be based on customer readiness. The final project plan will be agreed to between OpenText SaaS and the customer following project kickoff.
ALM environment diagram
This diagram illustrates the ALM SaaS environment and interaction between ALM and customer AUT environments.
Migration tasks
For details about SaaS migration, see the following instructions: